Overview
Saint Gobain – Nottingham
Saint Gobain were required to relocate to a new office location and chose an existing office development in Nottingham which had been unoccupied for several years.
Client
Saint Gobain – Nottingham
Location
Unit D1 Orchard Place, Nottingham, NG8 6PX
Industry
Construction & Manufacturing
Scope of Work:
Demolitions and Alterations
Electrical Works
Carpet Tiling
Lighting
Fire and Security Systems
Partitioning and Glazing
Ceiling Works
Flooring
Wall Finishes
Window Treatments
External Works
Cleaning
Project Details
Description of works
Saint Gobain were required to relocate to a new office location and chose an existing office development in Nottingham which had been unoccupied for several years. We were appointed by Project Sure for whom we had recently carried out a previous office fit out for ATS in Birmingham. This was a very similar project in which we refurbished 2 office floors and provided a plant area located on the second floor.
Stripping Out Existing Floors and Installing New Electrics
All of the existing floor finishes were stripped out and a small number of offices were demolished along with the ground floor comms room. This area had raised access flooring removed and replaced with a more suitable floor tile to match the open plan office area.
The office had no AC or ventilation installed so this was designed and installed by Vanguard’s trusted contractors along with the assistance of a client side mechanical and electrical engineer. The existing wet heating system was completely stripped out and the second floor turned into a storage area with a new Comms room.
A completely new electrical power and data installation was put in to all the new offices, canteens, meeting rooms and the main office areas. These were installed both through the raised access flooring into new floor boxes and into the newly formed stud walls. The meeting rooms and the open plan office area had new TV’s supplied and installed with power, data and HDMI services installed. New LED lighting was installed throughout with feature pendant lighting to the privacy booths. A new fire alarm system was installed with a new intruder alarm and a new access control system.
Transforming Old Spaces Into New
The fit-out had new stud partitioning and black framed glazing installed to provide the new canteens, meeting rooms and offices. The existing ceilings were removed to allow the M&E installation to be completed and new ceilings and tiles were installed upon completion of these works. The meeting room and canteen area had folding screens installed to allow the areas to be opened up when more room was required for meetings and lectures. New locker rooms were installed to both floors with the ground floor area being formed within a feature LED lit curved wall proving both the locker area and post room.
A brand-new kitchen and break out area was installed to the ground floor with new kitchen units, wall units, worktops, integrated dishwashers, and fridges along with a “Zip” tap facility. The first floor had the same installed to provide a smaller tea point facility to the first floor.
Facilitating An Open Plan Office Design
The new open plan offices, along with the newly formed offices and meeting rooms had new carpet tiling installed, set out to provide a bespoke patterns to create feature seating areas and walkways. Both the new kitchens, canteens and comms room had new vinyl flooring installed. All new and existing walls and joinery were prepared, and new decorations were installed to all areas along with feature wall vinyl’s. All the external windows had new blinds installed.
Externally, the existing plant area was not suitable for the new AC equipment being installed so it was demolished, and a new area was built with new service trenching, paving, and fencing. Adjacent to this, a new patio area was installed to provide an external area for the staff to take their breaks in. To access this area, an external glazed aluminium door was installed to a newly formed opening through the external fabric of the building. The client required EV charging facilities, so we installed the new trenching and base requirements for this facility.