Overview
Puccino’s – Richmond
An existing long-term Puccino’s franchisee wanted to expand their kiosk into an adjacent unit that became vacant. The scope was to expand the kiosk across both units making it into one larger unit.
Client
Puccino’s
Location
Richmond Train Station
Industry
Food and Drink
Scope of Work:
Demolitions and Alterations
External Joinery
Drainage and Plumbing
Electrical Works
General Joinery Works
Decorations
New Walls and Signage
Project Details
Installing the Necessary Hording
With the existing franchisee wishing to trade throughout the works, the project began out of business hours with us installing the necessary hoarding across both units. Temporary electric, water and data connections were routed to the hoarding externally to an access hatch, so our client could continue to provide their services to all commuters.
Refurbishing the Interior
A full internal strip out of both units was then followed by reconfiguration of the vacant kiosk to bring it level with its Puccino’s neighbour. A doorway was then formed between the two separate units opening up the footprint of the proposed build. After a full relining of the internal walls and ceilings, the building was ready to receive its refurbishment. The flooring was laid with full perimeter covering, followed by electrical works.
External Joinery and Drainage Works
External joinery work for the roller shutter enclosures and signage backing boards was completed in week three. With the previous Puccino’s kiosk having no drainage facilities, Vanguard installed a new pumping system from the new kiosk back into the back-of-house area of the train station. The twin pump system ran for 40 meters to the nearest drain. External spraying to existing roller shutters and frames, and all drainage works, were completed out of hours.
The Fit Out Final Touches
New surfaces arrived in week four and were swiftly installed, along with final wall finishes, decoration, external cladding, and electrical and mechanical services. Fridges, freezers and other vital equipment were also installed into the near-finished interior. Finally, new illuminated signage and full exterior graphics were added, along with the last of the general joinery works.
With the perimeter hoarding and temporary services removed, we completed the final handover on time and within budget, bringing together the various elements of our hospitality fit out services to deliver the expanded kiosk